Free PMI Risk Management Professional (PMI-RMP) Mock Exam

Pulled straight from the real question bank so you can judge the quality before you buy.

Question 1 of 10⏱ 08:00

A risk manager building the baseline for a hybrid-delivery data migration finds an industry benchmark showing an average 9% schedule overrun. The benchmark's sample consisted entirely of fixed-scope waterfall projects, while this project delivers in two-week increments with a changing backlog. The sponsor asks whether the 9% figure can serve as the schedule risk baseline. What is the best response?