Question 1 of 10Project Management Concepts

A retailer is replacing the point-of-sale software in 300 stores as part of a wider effort that also includes a loyalty app and a revised returns policy, all aimed at one customer-experience goal. The executive sponsor wants benefits tracked across the three pieces together. How should the PM position the point-of-sale replacement?